Scandia-Hus Build Diary

DSC_0254small

Update 8: Battening and Blockwork

Plasterboard ceilings Internally the ceilings on the ground floor have been prepared for the fixing of plasterboard. The ceiling has been battened and 15mm plasterboard sheets fixed to the timber battens. Insulation A final top level of insulation has been put into the roof and 47mm timber counter battens fitted on top ready for ceiling […]

Update 1: Groundworks

Update 1: Groundworks

The first stage of the build was to clear our site of all loose plant growth, cutting down hedgerows and overhanging branches from trees and generally levelling the site. We are using a straightforward trench fill foundation system. One metre trenches have been dug, filled with concrete and two courses of block work were laid […]