Update 14: Floor Screed

Now that the underfloor heating has been installed a floor screed is laid in order to protect the pipework. The pressure in the heating system is left on at this time.

The floor screed is a cementitious material made from a 1:3 ratio of cement to sharp sand. There are two routes that self-builders can select; opting for a ready mixed factory screed or a site mixed screed. The difference between the two is predominantly down to cost.

DSC_0006small

We have chosen a ready mixed screed which offers additional quality assurance and is a more consistent material.

DSC_0008small

The screed is piled up across the floor area. This is the entrance hall of the house, you can see the front door which is all covered up.

DSC_0039small

The screed is levelled and smoothed, creating a smooth finish.

DSC_0027small

DSC_0033small

The screed will be allowed to dry fully before any other work continues internally. In the meantime, work can carry on externally ready for the rendering.