Update 4: The Timber Frame Construction WK 2

It hardly seems possible that we have already completed the first week of our Show House build. The shell erection team have completed the first stage of the build and are now waiting for the roofing contractors to do their part

Day Six
Wintery day on site today

IMAG1228

Day Seven
Roof rafters are fixed to the ridge beam, you can see where the bank of veluxes are going to be placed

ShowHome3_20150203204300

Day Eight
The team spend the rest of today fixing the final roof rafters in place and finishing the roof overhang

ShowHome3_20150203232301

ShowHome3_20150204004301

Day Nine
The roof is sarked with 9mm OSB and fixed to the rafters with long galvanised wire nails

Day 9 file 1

IMAG1232

Day Ten
The breather felt was applied to the roof and counter battens fixed

IMAG1236

IMAG1241